South #InNetwork with Europe. Sustainable mobility restarts from here.

Follow us   

Palermo - Messina doubling: Fiumetorto - Ogliastrillo section

ig gp fiumetorto ogliastrillo en2The project is a phase of the entire track doubling project for the Palermo – Messina railway line, currently undergoing the works for the completion of the previous functional phases and the new upgrading works.

The project concerns the doubling of the railway tracks running between the stations of Fiumetorto and the Ogliastrillo interconnection. More specifically, it envisages the completion of the route affected by the doubling by finishing the activities already started in phase 1, so as to be able to activate the double-track connection along the entire section from Fiumetorto to Lascari and along the entire section from Lascari to Ogliastrillo.

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.1

  Start and end date: May 2008 - Dicember 2020

  Location of the intervention: Termini Imerese, Campofelice di Roccella, Lascari, Cefalù

  OP Contribution: 140,6 mln€

ico gis

Access the intervention webGIS service

 

Data updated in  February 2020

Per accedere al servizio webGIS del singolo intervento fare click sull’icona

  • Sistema dei Trasporti Salerno Porta Ovestico gis
  • Itinerario Bari - Taranto: Tratta S.Andrea - Bitettoico gis
  • Itinerario Palermo - Messina: Tratta Fiumetorto - Ogliastrilloico gis
  • Itinerario Napoli - Bari: Variante della Tratta Napoli - Cancelloico gis