Napoli - Bari route, 1st section: variant to the Napoli-Cancello line

IThe project includes the creation of a new double-track line, as a variant, 15.5 km long and allowing speeds up to 130km/h, 3 new stops, 1 new station and a new ACC-M – computerized multi-station central interlocking, with Controlled Point in Naples.

The completion of the works will also allow to suppress all 12 level crossings now present along the line, thereby improving the circulation of traffic on the local road system.

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.1

  Start and end date: October 2015 - December 2023

  Location of the intervention: Casoria, Caivano, Casalnuovo di Napoli, Volla, Afragola, Acerra

  OP Contribution: 151mln€

ico gis

Access the intervention webGIS service

 

Data updated in  February 2020

Per accedere al servizio webGIS del singolo intervento fare click sull’icona

  • Sistema dei Trasporti Salerno Porta Ovestico gis
  • Itinerario Bari - Taranto: Tratta S.Andrea - Bitettoico gis
  • Itinerario Palermo - Messina: Tratta Fiumetorto - Ogliastrilloico gis
  • Itinerario Napoli - Bari: Variante della Tratta Napoli - Cancelloico gis

IT - EN