Major Projects

Major Projects are large-scale infrastructure projects in transport, environment and other sectors such as research, energy or ICT. Major Projects benefit from financial support from the European Regional Development Fund and/or the Cohesion Fund. Their eligible cost must be more than € 75 million for projects under thematic objective 7 ("Promoting sustainable transport and removing bottlenecks in key network infrastructure").

OP Infrastructures and Networks'Major Projects.

 

Port of Salerno – rail and road connections

Port of Salerno – rail and road connections

Salerno Porta Ovest is a completion project aimed at eliminating the current bottleneck caused by the city road junction between the A3 motorway and the port infrastructure with related embarkation on ro-ro ships. It envisages the construction of a double-barrel tunnel (northbound and southbound lanes) that in the northern portion connects onto Via Risorgimento just prior to the intersection with Via Cernicchiara and, in the southern portion, to Via Ligea at the rear of the trade port.

The entire GP consists of two functional stages, only the first of which has been funded under NOP ‘Networks and Mobility’ 2007-2013. The project includes the construction of a double-barrel tunnel (northbound and southbound lanes), i.e.: a) The Northbound lane tunnel – total barrel length 2,493 metres; b) Southbound lane tunnel - total barrel length 2,469 metres. The typical cross-section of the bored tunnel has an average internal radius of 5.90 m and an excavation area of about 130 m2.

The average longitudinal slope of the two galleries is about 4.5÷4.8%. The effective width of the lanes, road side verges included, equals 8.25 m, and service sidewalks 0.60 m wide are also envisaged.

Identity card of the intervention

  Beneficiary: Port System Authority of the Central Tyrrhenian Sea

  Action Line: II.1.2

  Start and end date: September 2013 - June 2019

   OP Contribution: 60,6 mln€

Bari - S. Andrea Bitetto line doubling

Bari - S. Andrea Bitetto line doubling

The project consists in the doubling of the Bari S. Andrea-Bitetto railway line and aims at streamlining the direct travel of passengers between the port of Taranto and the port of Bari, the Adriatic railway line, the junctions with the Bari-Napoli route, the logistic district of Bari and the airport of Bari.

The structures, achieved almost entirely by deep cutting, cross through the municipalities of Bari, Modugno and Bitetto. The project includes the technological equipment and superstructure installation along the entire section, the building of a new intermediate station - “Bari - Villaggio dei Lavoratori” – and the “Modugno” stop, as well as a communication post at chainage Km 5+650.

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.1

  Start and end date: January 2013 - October 2019

  Location of the intervention: Bari, Bitetto, Modugno

  OP Contribution: 90,0 mln€

Metaponto - Sibari - Paola (S. Antonello Junction): Priority phase

Metaponto - Sibari - Paola (S. Antonello Junction): Priority phase

The project is phase 2 of the Grand Plan “Upgrading of Metaponto-Sibari–Paola (Bivio S. Antonello): priority phase”, divided into 4 functional lots.

The MP will result in: 1) the upgrading of the contact line (Trebisacce – Sibari – Castiglione Cosentino) for a total of 59.8 km. Compared to the total 74.1 Km involved in the upgrade, 14.3 km refer to route variants the tenders of which also include the upgrading of the technical equipment (see below); 2) route variants (Cassano, Tarsia, Torano and Acri) for a total of 14.3 km; 3) lengthening to module 740 m of 2 systems (Torano and Amendolara).

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.2

  Start and end date: February 2014 -  June 2019

  Location of the intervention: Acri – Amendolara – Cassano all'Ionio - Castiglione Cosentino – Mongrassano - Montalto Uffugo - Rocca Imperiale Rose - San Marco Argentano - Spezzano Albanese – Tarsia - Torano Castello - Trebisacce

 OP Contribution: 99,7 mln€

Palermo-Messina doubling - Fiumetorto - Ogliastrillo section

Palermo-Messina doubling - Fiumetorto - Ogliastrillo section

The project is a phase of the entire track doubling project for the Palermo – Messina railway line, currently undergoing the works for the completion of the previous functional phases and the new upgrading works.

The project concerns the doubling of the railway tracks running between the stations of Fiumetorto and the Ogliastrillo interconnection. More specifically, it envisages the completion of the route affected by the doubling by finishing the activities already started in phase 1, so as to be able to activate the double-track connection along the entire section from Fiumetorto to Lascari and along the entire section from Lascari to Ogliastrillo.

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.1

  Start and end date: May 2008 - Dicember 2017

  Location of the intervention: Termini Imerese, Campofelice di Roccella, Lascari, Cefalù

  OP Contribution: 140,6 mln€

Speeding up of the Catania-Siracusa (CT-SR) route - Bicocca -Targia section

Speeding up of the Catania-Siracusa (CT-SR) route - Bicocca -Targia section

The project consists of the 1st functional block Bicocca – Augusta, that corresponds with Phase 2 of the GP

The implementation of the Bicocca–Augusta section entails the following main works:

  • 7 route variants;
  • overhaul of the existing works in order to ensure their durability;
  • restoration of the water management works (diversion ditches, delivery channels, etc.);
  • escarpment stabilization works (riveting, retaining walls, scaling with stone blocks, etc.);
  • underpassage, stairs, ramps in the Lentini station;
  • implementation in the station structures of escape tracks;
  • creation of technological niches inside the Valsavoia tunnel;
  • adaptation to the minimum requirements envisaged by Min. Decree 28/10/2005 “Safety in railway tunnels” for the existing 1519 m long Valsavoia tunnel;
  • construction of 3 new flyovers and of 2 channel bridges.
Additionally, the project envisages works on the systems in:
  1. Stations: Lentini Branch (on the CT-SR line it acts as shunting yard) (km 248+761) and Lentini (km 254+315)
  2. Shunting yards: (the structure of Passomartino has already been eliminated during the DTP works); Agnone di Siracusa (km 263+490); Brucoli (km 274+979).
  3. The project works envisage all of the interventions on the safety and signaling systems, telecommunication systems, electric traction and superstructure, as well as noise mitigation operations, in some sections via the application of noise barriers and in others via direct intervention on the receptors.

    Identity card of the intervention

      Beneficiary: RFI - Rete Ferroviaria Italiana

      Action Line: I.1.2

      Start and end date: November 2015 -  June 2021

      Location of the intervention: Augusta, Carlentini, Catania, Lentini

      OP Contribution: 75,3 mln€

Palermo railway hub: La Malfa/EMS-Carini section

Palermo railway hub: La Malfa/EMS-Carini section

The project consists in the doubling of the EMS/La Malfa–Carini section divided into two sub-sections; in addition to the completion of the works started in the Phase, the sub-section EMS/La Malfa-Isola delle Femmine will also receive an emergency speaker system; adaptation of the railway platform using anti-vibration sub ballast; emergency circuit cable system.

The sub-station Isola delle Femmine-Carini will receive an emergency speaker system; landscaping; emergency circuit cable system; Capaci landfill road system.

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

   Action Line: I.1.2

   Start and end date: February 2008 - Dicember 2018

  Location of the intervention: Palermo, Isola delle Femmine, Capaci e Carini

  OP Contribution: 17,9 mln€

Palermo -Catania -Messina main railway. Doubling of the Bicocca-Catenanuova section

The project includes the creation of a variant of the railway line exiting from the Bari Centrale station and heading south, along the Bari C.le – Bari Torre a Mare section.

The works will cover a total stretch of about 10.5 km and the line speed will be 160 km/h with several limits along the section coming out of Bari Centrale. The project also envisages the creation of two new structures: the “campus” stop and the “Bari Executive” station.

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.1

  Start and end date: October 2015 -  Dicember 2022 

  Location of the intervention: Catenanuova, Centuripe, Paternò, Belpasso, Motta S.Anastasia e Catania

   OP Contribution: 135 mln€

Napoli - Bari route, 1st section: variant to the Napoli-Cancello line

IThe project includes the creation of a new double-track line, as a variant, 15.5 km long and allowing speeds up to 130km/h, 3 new stops, 1 new station and a new ACC-M – computerized multi-station central interlocking, with Controlled Point in Naples.

The completion of the works will also allow to suppress all 12 level crossings now present along the line, thereby improving the circulation of traffic on the local road system.

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.1

  Start and end date: October 2015 - October 2022

  Location of the intervention: Casoria, Caivano, Casalnuovo di Napoli, Volla, Afragola, Acerra

  OP Contribution: 151mln€

Napoli - Bari route, doubling of the Cancello-Benevento section

The section involved is 16 km long and envisages the speeding up and doubling of the old line, partly by running alongside the current line and partly as a variant (over a distance of about 6 km).

Identity card of the intervention

  Beneficiary: RFI - Rete Ferroviaria Italiana

  Action Line: I.1.1

  Start and end date: October 2015 -  April 2023

  Location of the intervention: Dugenta, Frasso Telesino, Sant’Agata de Goti, Maddaloni, S. Felice a Cancello, Valle di Maddaloni, Cervino

  OP Contribution: 165 mln€

 

Intervention categories

Rete Ferroviaria Railway Network

Intervention fields Reg(UE) 215/2014
  • 024 - Railways (TEN-T Core)
  • 025 - Railways (TEN-T comprehensive)

Read more

Porti e intermodalità Ports and multimodality

Intervention fields Reg(UE) 215/2014
  • 035 - Multimodal transport (TEN-T)
  • 039 - Seaports (TEN-T)

Read more